Friday, August 29, 2008

Making Progress




Framers are finally on their way out, windows going in, roofing is started, HVAC is started...

Tuesday, August 26, 2008

Slow Going




With threats of having everything done in the next 2 weeks, framers are still on site finishing up the details so the pressure is off for now. Should see plumber, electrician and HVAC all on site this week....sometime.

Monday, August 25, 2008

Quick Update


Been busy, but we all checked out the house this weekend, not really much progress plus we were on the run.

Thursday, August 21, 2008

No Roof!



I don't know what happened, they didn't set the roof joists yesterday but they did clean up and do some miscellaneous framing. The front door is starting to take shape and this is the kitchen to the family room (still haven't fixed the windows) with the morning room off the back.

Wednesday, August 20, 2008

2nd Floor Continues




Just a quick one with a few pictures. They are setting roof joists today, so might be a big update tomorrow

Saturday, August 16, 2008

Second Floor Started


Doesn't look like much but all of the flooring is down, they are going to set the stairs in place and will rent a crane to set roof joists on Wednesday.

Thursday, August 14, 2008

Framing about 1/4 done





I had a camera malfunction this week, so missed the first few days of framing, so this is after 4 days of framing. They started on Friday of last week and these pictures were taken Wednesday night.

I've only seen 2 problems so far, they put the family room windows in the wrong spot and are using a floor joist that looks like it is about 3 years old.

Powder room and Mud room look a lot smaller than they do on paper, but should be OK

Tuesday, August 12, 2008

Not Much Activity on the House





House is moving slow, they started some framing last week, but have not got very far so here are some good pictures of Jack and Kyle at Sharon Woods Park running through some water fountains.

Tuesday, August 5, 2008

Basement Floor, Steel and Garge




Well, small steps of progress with more questions.. egress window is too high, a low spot in the garage floor and misc. metal (that's for you DPL) is interfering with my finished basement plans.

Wood is delivered to start framing this week.

New Fishermen




The Brooks Brothers are quite the fishermen, although they didn't catch a thing, sure had fun trying.